1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32 | LPA conducted interviews with staff 1 (S1) thru 7, child 1 (C1) thru 3, and parent 1 (P1) thru 4. LPA also obtained a copy of the facility roster. LPA received copies of the lead and asbestos reports dated 09/10/24, 10/08/24, and 10/24/24. LPA also received a copy of the Procedure-5 Asbestos Abatement Work Plan dated 10/28/24.
Allegation regarding- Licensee did not ensure that the facility materials and surfaces accessible to children was free of toxic substances. According to the RP, on 09/30/24, removal of the roof began and observed debris floating into the air as roofing materials were thrown from the rooftop into an open truck bed, making the parking lot and church compound dusty. RP stated that they didn’t know if the roof materials were tested prior to removal. Per RP, a message sent via the app Lillio stated: "Inside the preschool area had very little dust, but it has been swept, washed down" and "the children are using the side playground to play." RP also disclosed that the sign in sheets had a layer of dust. Picture of the sign in sheet was provided and reviewed by LPA. RP also stated that their child was covered in dust; however, no picture or other form of corroborating evidence was available. On 10/18/24, the RP received a message through the Lillio parent communication app which notified parents that the facility tested positive for lead and asbestos in the building where construction was taking place. According to the RP, the message lacked detailed information of when the facility first conducted the lead and asbestos test, when the results were received, the abatement plan to properly remove the contaminated items, and who the licensed contractor is. Children were moved to another licensed area on campus on 09/27/24 and used the “small” playground for outdoor play.
The following reports were provided to LPA for review:
Lead report dated 09/10/24 states that the second-floor room 5 (floor) tested positive for lead.
Asbestos report dated 09/10/24 states that the second-floor room 1, 2, 4 and 5 floors tested positive for asbestos.
According to the reports mentioned above, the initial testing was done on the second floor of the Eave Building. The report includes recommendations and disposal requirements the facility must follow and should consider “If additional suspect materials are found at the property and will be impacted by demolition, renovation, or reconstruction activities, they must be assumed positive for asbestos or tested prior to disturbance.”
Page 2 of 5 |