25 | This unannounced inspection is being conducted by Licensing Program Analyst (LPA) Sean Haddad for the purpose of following up on construction plans for renovating the kitchen floor submitted to the Orange County Regional Office (OCRO) on 06/27/23. LPA met with Administrator (AD) Maria Domingo and explained the purpose of the inspection.
During the first inspection on 07/03/23, LPA inspected the facility and reviewed the facility’s plans for the kitchen floor renovation. Per AD, the kitchen floor renovation project was completed on 08/11/23, there were no issues related to the project, and the facility returned to normal kitchen operations.
During today’s inspection, LPA and AD toured the kitchen. LPA observed the floors were replaced as part of the kitchen floor renovation project and the kitchen contains all necessary fixtures, tables, appliances, and equipment. LPA observed the kitchen to be clean and organized and observed no health and safety issues. LPA observed the facility has a 2-day supply of perishables and a 7-day supply of non-perishable food. LPA observed lunch was being served with residents eating in the dining room. LPA confirmed the kitchen floor renovation project has been completed without issue.
There were no health and safety concerns observed in the areas inspected. Based on the observations made during today’s inspection, no deficiencies are being cited per Title 22 Division 6 of the California Code of Regulations. An exit interview was conducted and a copy of this report was discussed with and provided to facility representative. |