1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32 | Sonray Construction began the roofing work, however, Paragon Construction is completing the additional scope of work required by the Engineer for the permit.
A copy of the Paragon Construction contract dated 3/28/24 which was initiated 3/26/24 was provided.
The inside areas of the dining room such as the carpet, mold inspection, painting will be completed within the next 2 weeks.
An incident report was submitted to Community Care Licensing (CCL) as well. A report of completion shall also be submitted to CCL.
Based on interviews and a review of documentation the allegation is deemed Unfounded.
"The allegation is UNFOUNDED, meaning that the allegation was false, could not have happened and/or was without a reasonable basis. This Department has therefore dismissed the complaint." Per California Code of Regulations, no deficiencies were observed or cited. Exit interview held, and a copy provided. |