25 | On 7/29/22 at 2:15pm Licensing Program Analyst (LPA) Kevin Gould conducted an unannounced Plan of Correction (POC) inspection to ensure deficiencies cited during a previous complaint investigation had been completed per the agreed upon POC.
LPA observed documentation of scheduled training for staff members regarding the plan of correction.
LPA has cleared the deficiencies and generated a POC clearance letter.
While at the facility LPA observed the wooden ramp leading to the facility has a spot where the wood has rotten and become soft and has become a potential tripping hazard for residents and visitors. An advisory note was left at the facility indicating a requirement to repair the ramp.
Per California Code of Regulations, Title 22 there were no deficiencies cited during today's inspection. An exit interview was conducted, and a copy of this report was left at the facility. |