25 | On August 24, 2023 at 03:16 p.m., Licensing Program Analyst (LPA) Kendal Zirbes conducted an unannounced Plan of Correction (POC) inspection and met with facility representative Zaray Ochoa. LPA disclosed the purpose of the inspection and was granted entry into the facility by the Facility Representative. 37 preschool age children, four teachers and additional administrative staff members were present.
During this inspection, LPA and facility representative Zaray Ochoa completed a tour of the facility. LPA observed the following:
1. The extension cord running on the floor between the two classrooms was removed.
2. Electrical outlets were inaccessible to the children in care
3. An invoice from an electrician was received.
Based on LPAs observation, the deficiency cited on 8/23/2023 have been corrected.
A notice of site visit was given and must remain posted for 30 days. Exit interview conducted and report was reviewed with the Facility Representative Zaray Ochoa. |