1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32 | The facility has 14 large bins that contain required emergency supplies, and these are stored as follows: Main building has seven (7) bins total, three(3) on the 1st FL, two(2) on the 2nd Fl, and two(2) on the 3rd Fl. The South building has three (3) bins, one on each floor, and the North building has two(2) bins, one on each floor; North and South Casita's each have one large bin for each Casita area. Fire extinguishers, 207 in main bldg, 12 in North bldg, and 20 in South bldg, were all serviced and tagged as required- 4/11/2023. LPA observed all lock boxes, main bldg, North and South bldgs posted up, all have emergency set of keys. The facility vehicle keys were available in the lock box as well. LPA observed facility generators were located in each garage (3 of 3) and were working appropriately. Facility has evacuation chairs at each stairwell, Main bldg has five(5), South bldg has two(2), and the North bldg has two(2), as required, including instruction manuals for use. Hot water in the main building was checked at 116.7F and 114.6F, North building was checked at 120.F and the South building was checked at 120.F. Maintenance Director Ferrarese will monitor the hot water to ensure it is maintained at no lower than 105.F and no higher than 120.F which is within regulation. Facility had sufficient lighting in all common areas, hallways, restrooms observed, and in all buildings. The facility had sufficient supply of cleaners, hygiene products, and paper products. Toxins are locked up and secure as required. All housekeeping carts checked by the LPA during the tour were observed to be locked as required. Medications are locked and inaccessible to residents in care, including staff that don't handle medications.
LPA reviewed staff records, including training. All staff have required criminal record clearance. All staff were found to have the required first aid and CPR certification per regulations. Staff records were complete. LPA reviewed resident records. Resident records were found to be complete.
LPA reviewed emergency disaster, fire drills and evacuation drills; The following are some of the drills from 2023 & 2022: On January 25-2023 facility had an emergency flood drill, February 23-2023 power failure drill, March 31-2023 a wild fire & evacuation drill, April 26-23 a gas explosion drill, evacuation drills were conducted on March 31-22 and September 7-22. Due to the rain the 2023 evacuation drill was cancelled but has been rescheduled.
Continued on LIC809C... |