1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32 | LPA also inspected the 6 generators on-site at the facility. One generator in each garage, Main garage, South garage, and North garage. These garage generators have transfer switch boxes connected to the generator; In the event that there is power loss to the facility, the transfer switch boxes will utilize the power from the generator to open the garage doors in an emergency and/or for use.
There were two other generators posted out in two other areas of the facility ready for use in an emergency due to the recent fire in the County, and PGE possible shut offs of electricity.
One generator was in the storage work shop, where signs identify where to locate the three (3) generators for emergency use, one of the three was here that was not in use/ready for use. LPA observed each generator, all 6 generators, with the instructions attached, and all generators worked properly as the Maintenance Director started each one up so the LPA could observe them.
Elevators were inspected on 10/6/20 in all buildings, 4 in the main building and one each in South building and North building-all passed inspection. Fire Panel in all buildings, and fire Sprinklers was inspected, 1/8/20, 1/17/20, 4/17/20, 7/23/20, and 7/24/20, all fire sprinklers and fire panels passed inspections, in the Main building, South Building, and North building.
LPA inspected additional records with Debbie Smith, Assistant Administrator Executive Director.
Fire drills are being conducted as required. Last fire drill was 9/15/20 during NOC shift. Active Shooter Emergency Disaster Drill was conducted on all three shifts, AM, PM, and NOC shift-held on 9/15/20. On July 29 during AM & PM held evacuation training. On 7/30/20 the facility held an AM Evacuation drill which met the 80% participation required; Many residents participated with some staff stand ins.
Continued on LIC809C... |